See The Gully Erosion Sites Where Intervention Has Been Made During The Okezie Ikpeazu Administration:

Kinetic Abia:

Some of the gully erosion sites where intervention has been made during the Okezie Ikpeazu administration are as follows:

1. Amuzukwu Ibeku gully complex in Umuahia North LGA. A total of 2km of internal roads around the gully area were constructed.

  1. Umuezeukwu Nsulu gully site in Isialangwa North LGA. The gully was fully remediated and a road length of 2.5Km with side drains was constructed from Umuezeukwu to Umuezenta Mbawsi
  2. Amuda -Achara gully site in Umunneochi LGA. The gully has been fully remediated and 1.8km of road with side drains and culverts constructed
  3. Umuogele Umuakwu Nsulu in Isialangwa North LGA. The gully has been fully remediated and 2.5km of road with side drains, pedestrian walkway and a bridge across the Umuakwu river constructed
  4. Umuagu Ibeku- Umuda and Amafor Isingwu gully complex in Umuahia North LGA. The gully has been fully remediated and a total of 5.8km of roads constructed. The roads comprise 2.4km of internal roads in Umuagu Ibeku and 3.4km road from Umuda Isingwu through the Isingwu community to Ossah Ibeku

IkpeazuSabiTheWork

KineticAbia

About Thebridgenewsonline

Check Also

IKWUANO AGOG FOR IKECHI EMENIKE: AS PARTY FLAGS – OFF THEIR GOVERNORSHIP TOUR.

IKWUANO AGOG FOR IKECHI EMENIKE: AS PARTY FLAGS – OFF THEIR GOVERNORSHIP TOUR. It is …

Leave a Reply

Your email address will not be published. Required fields are marked *